Overview

As part of the Level Crossing Removal Authority (LXRA) program to eliminate Melbourne’s most dangerous and congested level crossings, a 2x4MW Southern Cross substation was created to upgrade the traction power system, a task identified through modeling as necessary to support the future deployment of High Capacity Metro Trains (HCMT) on the Metro Trains Melbourne (MTM) network.

Challenge

Developing a multi-story substation equipment layout design and optimization. Creating a 11 kV AC, 1500 V DC, low voltage AC and DC, communication and control cable reticulation design that supports 1500 V DC feeder interface design. Additionally, ensuring a negative return current system/track interface design.

Solution

Middleton Group played a key role in the design management, electrical and structural detailed design vendor interfacing and construction phase. It was necessary to develop architectural, structural, civil, mechanical, electrical, power, overhead wiring and earthing deliverables to a detailed design standard required to clearly articulate the project and design intent.

Results

The team’s expansive knowledge in design management and electrical design allowed for all options for be evaluated and the most beneficial chosen to allow for an efficient project

Contact us

Keith Middleton

Managing Director