Overview Cathedral Rocks Wind Farm is located approximately 30km southwest of Port Lincoln. The wind farm consists of 33 wind turbines and generates 66 MW…
Overview The RayGen Power Plant Carwarp Project is a ground breaking dispatchable renewable electricity project that will provide reliable, on-demand power to the distribution network…
Overview To achieve Sydney Water’s Energy Management and Climate Change goal, Sydney Water have been investigating options to improve their energy efficiency and prepare for…
City West Water (CWW) has identified an opportunity for solar development at their Werribee Recycled Water Treatment Plant (WRWTP) and has asked for our assistance…
The Darlington Point Solar Farm is a 333MW DC single-axis tracking project located south of the town of Darlington Point. The project has an approximate…
Middleton Group was involved in reviewing the design (30%, 60%, and 90%) to install a 220kV interconnector cable between the Mortlake South Wind Farm and…
Middleton Group were asked to provide a comparison between connection options, to identify optimal connection methodology: 220 kV transmission connection or 66 kV sub-transmission connection.